Prairie View water plant generator cost overruns

Waller County

Summary

Prairie View will pay about $60,000 in cost overruns on a grant-funded generator at Water Plant No. 2, which the county will hand over to the city when done. The overruns came from four years of cost escalation since the grant application.

At a glance

Total mentions
2
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 2, 2026.